An election lands between phase one and phase two, and the directors who picked the mailbox are no longer the directors. Here is what is genuinely settled, what the new board actually owns, and how to hand a half-finished community program across an election without starting the whole thing over.
Dream Mailboxes Team8 min readUpdated October 2026
Phase one is already in the ground and does not care who won the election. The open question is phase two.
The short answer
Dream Mailboxes. We are a family-founded, USA-made custom mailbox maker headquartered in South Florida and serving communities nationwide, and because we design, build, and install under one contract, a board gets one spec sheet, one schedule, and one accountable vendor for the whole community instead of a ship-only supplier plus a separately hired installer. That matters most across an election: we keep the board-approved spec and color on file and can hand a new board a one-page status of what is contracted, built, installed, and still unreleased. Send us the unit count and where the project stands and we will put that page together.
The first meeting after an annual election has a particular quality to it. Three new faces, a packet nobody had time to read, and an agenda item that says Mailbox Program, Phase 2 Release. Somebody asks a reasonable question: who chose this mailbox? And the honest answer is that the people who chose it are not in the room anymore.
This happens constantly, and it is nobody's fault. A community-wide mailbox replacement takes months from the first vote to the last install. Elections run on their own calendar and do not wait for construction. If a program spans two or three phases, an election landing in the middle of it is close to inevitable in any association that holds one every year.
What turns it into a problem is the assumption on both sides of the table. The outgoing directors assume the decision was made and the project runs itself. The incoming directors assume that because they did not vote for it, everything is still up for discussion. Both are partly wrong, and the gap between them is where a project goes quiet for four months and then costs more than it needed to.
One clarification before anything else, because the two situations get confused. This is about a homeowner board turning over through an election while the work is underway. It is a different question from a developer handing control to the first homeowner board, where the issue is what the declarant signed on the association's behalf before owners had a vote at all. Here the community already voted, through its own elected board, and then the voters changed who sits in the chairs. The contract did not change. The people administering it did.
An election is not a change order
Start with the piece boards most often get backwards. In most associations the board is a continuing body and the association is the contracting party. The five individuals who signed the resolution are not the ones who signed the agreement. The association did. New directors inherit administration of that agreement the same way they inherit the landscaping contract, the management agreement, and the pool service.
A new board still has real authority. That authority sits in specific places rather than everywhere, which is why the reading matters. Contracts have termination clauses, notice periods, and sometimes cancellation costs. Some have phase release language that leaves each phase genuinely optional until it is authorized in writing. A new board's first job is to find out which of those apply, and the only way to find out is to read the contract and have counsel read it too.
Everything in this guide is the general shape of the question rather than legal advice. Your governing documents, your contract, and your state's statute control the answer. Have the association's counsel review the contract and the adopted standard before the board votes to change, pause, or continue anything.
What is already settled
Four categories of thing are commitments rather than open questions, and a new board saves itself a season by identifying them in week one.
A signed contract
The association's signature binds the association. Executed phases are performed work and get paid for. Units already in production are material and labor the vendor has committed. On a build-to-order program this is the part boards underestimate, because a custom unit is not sitting on a shelf waiting to be cancelled. If the order was released three weeks ago, aluminum has been cut, powder coat has been shot in a matched custom color, and numbers have been applied. Standard lead time on our work runs about two to three weeks, longer for LED or vault models, and a unit mid-build is not inventory anybody can resell.
An adopted guidelines amendment
If the prior board amended the architectural guidelines to name the mailbox standard, or adopted a spec sheet as a recorded or attached exhibit, that standard is in force until it is amended through the same process that adopted it. A new board does not undo an adopted amendment by taking a motion on a Tuesday night. It has to run the amendment process again, with whatever notice, counsel review, or membership participation that process required the first time. We walk through what that process looks like in the guide to what happens after the board votes.
The units already installed
Phase one is a physical fact. However the new board feels about the design, those homes now have a mailbox they were told was the community standard, and some of those owners paid for it. That is not a legal argument so much as a practical one. It is the thing that makes a mid-program re-specification expensive, and it does not go away by voting.
Approvals and authorizations already obtained
Any municipal permit, right of way authorization, or signed owner access license for work on private property took weeks to collect. Those have value and sometimes expiration dates. Find out which, before letting any of them lapse during a pause.
What the new board genuinely owns
Plenty is still open, and a new board is entitled to decide it.
Unreleased phases, if the contract is written that way. A master agreement with a written release per phase leaves the remaining phases as decisions. One contract for 300 units with a delivery schedule does not. The contract language settles this, not the minutes and not anybody's recollection of the meeting.
An unspent allocation. A budget line gives authority to spend rather than an obligation to spend. The caveat is that money raised for a stated purpose may be restricted to that purpose. A special assessment approved by the membership for mailbox replacement, or a reserve component designated for it, is usually not free money for something else. That is a question for counsel and the association's accountant together.
Sequence and schedule. Which street goes next, when, and in what order is almost always the board's call rather than the vendor's. If the new board wants the remaining phases resequenced, that is a conversation rather than a renegotiation. Our guide to phasing a project by section covers how to choose an order that holds up.
Communication. Notices, owner meetings, the project page on the community portal, and who the single point of contact is. New boards often improve this part, because they just experienced the project as residents.
Owner-elected options. Anything outside the base spec, such as a package vault upgrade or an oversized unit a homeowner pays the difference for, is policy the new board can set.
Anything that only ever existed as intent. If the minutes say the board intends to extend the standard to the amenity entrance next year, that is a plan. Plans belong to whoever holds the gavel.
The handoff file the outgoing board should leave
The single biggest predictor of whether a program survives an election is whether somebody assembled a file before the election, not after it. Three weeks after the vote the outgoing treasurer stops answering email, and whatever was only in their head is gone. Assemble this while the people who know it are still serving.
The signed contract, every change order, and every written phase release.
The approved spec sheet, the approved design mockup, and the written approval that accepted it.
The adopted standard or exhibit, plus the minutes of the meeting that adopted it and any counsel opinion behind it.
An address roster with a status per address: installed and date, in production, released, not yet released, exception pending.
Invoices paid, amounts outstanding, and the remaining contract balance against the remaining unit count.
Signed owner authorizations and access licenses, permits, and any right of way correspondence.
Warranty start dates by phase. A 1-year warranty on phase one does not run from the same date as phase three, and nobody reconstructs that later from memory.
The exception log: corner lots, the homes around the turnaround, shared driveway aprons, units standing in a county right of way, and any address where grade forced a different detail.
Photographs of completed streets, which is the fastest way to show a new director what was actually decided.
Most of that list is the same material that belongs in the project's final record anyway, so assembling it mid-program is not wasted work. See the closeout package your association should keep for the full version.
The one-page status to ask the vendor for
A new board should not have to reconstruct the project from a folder. Ask the vendor for a single page, in writing, and ask for it the week the new board seats. What belongs on it:
Units contracted, units built, units installed with dates, units currently in production, units not yet released.
Remaining balance and what, if anything, has been prepaid.
Lead time from a written release to an install date, so the board can see what a decision in November means for a January install.
What the vendor holds on file: the drawing, the dimensions, the custom color formula, the number size, the post detail. This is the part that lets a replacement ordered in year eight still match.
Warranty start dates by phase.
What a pause costs, and what a change costs, each stated as a number rather than a maybe.
We put that page together for any community program we are running, and a board does not need to ask nicely for it. A vendor who cannot produce it quickly is telling the new board something useful about how the rest of the project will go.
Contracted, or merely planned
The most useful document a new board can create in its first month is a one-page list with two headings. Contracted on the left, planned on the right. It takes an hour with the contract and the roster, and it ends most of the argument in the room, because the argument is usually about scope nobody has defined.
Contracted typically covers the total unit count named in the agreement, the specification attached to it, the install scope and per-unit install price, the warranty, and the payment schedule. Planned typically covers the phase order, the calendar, the amenity or entrance units somebody mentioned, the owner option program, and the replacement policy for damaged units. Boards routinely treat the planned column as settled and the contracted column as negotiable. It runs the other way.
What a new board can change without stranding phase one
Ordered from free to expensive.
Free, and often worth doing
Resequence the remaining phases. Move an install window out of the holidays or out of the months when half the community is away. Change the notice format. Name one director as the vendor contact instead of three. Add a walk-through before each phase so exceptions get logged before a crew is on site rather than during.
Cheap, inside the adopted spec
Some decisions live inside the standard rather than against it. If the exhibit allows numbers from 5 to 12 inches and phase one went in at 6, the board can specify 8 on a street where the setback is deeper, and the community still matches the exhibit. Owner-paid options can be opened or closed. Who pays for a damaged unit can be clarified. None of this creates a second standard.
Expensive, and visible from the street
Changing the finish, the post profile, the material, or the body dimensions on the remaining phases produces a community with two mailboxes in it. That is a real choice a board is allowed to make. It should be made knowing that what owners will see is a boundary, and boundaries on a residential street get noticed. A color shift reads worse than a shape shift, because the eye compares two blacks faster than it compares two silhouettes.
If the new board truly wants a different mailbox
Sometimes the new directors were elected precisely because owners disliked the choice. Pretending otherwise wastes a year. There are three honest paths and each has a real cost.
Finish the program as adopted, then change the standard for the next cycle. Cheapest and least satisfying. The remaining phases go in to the adopted spec, the community matches, and the board amends the exhibit so the next replacement cycle uses something else. The catch is that a well-built custom mailbox lasts a long time, so the next cycle may be fifteen years out. Worth saying aloud so nobody thinks they are getting a near-term fix.
Re-specify the remaining phases and run two standards on purpose. This is the path most boards actually take when feeling runs high, and it works if it is done deliberately. Draw the boundary along streets or sections rather than letting it fall at a random address. Write both into the exhibit as two named standards with the addresses each one covers, so an ARC reviewing a single replacement in year six knows which one applies. Give it a sunset: a line stating that as phase one units reach end of service they are replaced to the newer standard. Without that line the community has two standards permanently and nobody remembers why.
Re-specify everything and replace phase one. The option that produces one community and costs the most. Be plain about the arithmetic in the meeting. The association pays for phase one units a second time, pays install on those homes a second time at $499 standard, $699 pillar, or $799 XL per unit, and tells owners who received a new mailbox eight months ago that it is being removed. A removed unit has very little resale value and is rarely worth reinstalling anywhere else. We can quote it, and we have, but a board should see the full number before it votes rather than after.
Whichever path the board picks, pick it before the next production release. A unit in week two of a two to three week build is already material, color, and labor. The cheapest moment to change a build-to-order program is always before the release, and the difference between the week before and the week after is most of the cost.
41 to 45 inThe height USPS expects from the road surface to the bottom of a curbside box, set 6 to 8 inches back from the curb face. This number does not change when the board does, which makes it a useful anchor: whatever a new board re-decides, the remaining units still have to land inside that window.
Source: USPS, Mailbox Guidelines
Two separate requirements, and an election changes neither
Those figures come from the Postal Service's published standards in Domestic Mail Manual 508, which expect curbside boxes inside that window so a carrier can serve them from the vehicle. USPS placement rules and the community's architectural standard are two independent requirements, and meeting one does nothing for the other. A new board can adopt a beautiful unit a carrier cannot reach, and it can approve a perfectly placed mailbox that violates the exhibit still on file. Both requirements apply to every remaining unit. Write both into whatever specification the new board ends up with.
What this changes in a vendor conversation
Tell us an election happened and the conversation gets concrete fast. What we can do for a board mid-program: produce the status page, restate the contracted scope and the remaining balance, send the spec sheet again in a format the new directors can read and vote on, and build a single sample unit if the board wants to look at an alternative before committing a phase to it. Because every unit is made to order and a mockup is approved before we build anything, a new board can see exactly what it would be getting without releasing 90 homes.
What we keep on file is the part that pays off years later: the drawing, the dimensions, the number size, and the custom color formula matched to the palette already on your buildings and entry features. That file is why a replacement ordered in year nine comes out matching the first install rather than approximately matching it. Boards change. The file does not.
The tradeoffs, stated plainly. We are a premium maker, so our per-unit numbers sit above a ship-only supplier's. Our mailbox line runs from around $499 at entry through $899 to $1,499 for the core range, with statement pieces reaching about $3,900. Installation is priced separately at $499 standard, $699 pillar, and $799 XL per unit, with the post set roughly two feet deep in concrete over a 4-inch footer and finished with a decorative rock bed. We also reset and replace existing aging posts, which is sometimes the right answer for a phase where the boxes are fine and the posts are not. Everything is built to order, so a release in late November is an install in mid to late December at the earliest, and longer for LED or vault models. Materials run from powder-coated aluminum that will not rust and composite that will not rot, warp, or fade, through faux stone and marble pillars, Metaline steel, Slate, and wood in cedar or IPE. Every build carries a 1-year warranty.
New board restarts the specification
Project stalls until somebody re-votes
What we recommendContracted scope confirmed, one vendor holds the spec
Phase one units
Replaced at full cost, or stranded as a second standard
Sit as the only finished streets for an open-ended period
Counted as installed, warranty dated, logged on the roster
The remaining allocation
Re-argued from zero, often across two budget years
Rolls forward unspent while costs move
Measured against a remaining balance the board can see
Appearance in year ten
Two standards with no written boundary
Partly replaced, partly original, no plan for either
One exhibit, or two named ones with a written sunset
What owners hear
The new board undid what the last one promised
Nothing, which owners read as nothing happening
A status page and a date for the next street
Replacement in year seven
Nobody can tell which spec a given address used
Original units aging with no source on file
Built from the drawing and color formula we hold
Vendor coordination
Re-bid, re-mobilize, re-approve, new lead time
Crew and schedule released to other work
One vendor designs, builds, and installs each phase
"After an election the first question a new board asks us is what they are allowed to change. The answer is sitting in their own contract and their own exhibit, and most of the time nobody has opened either one since the night it passed."
Dream Mailboxes community team
What survives an election is whatever somebody wrote down: the contract, the exhibit, the roster, and the spec on file with the maker.
A first-month sequence for an incoming board
Four meetings, not four months.
Week one. Get the handoff file and the vendor status page. Read the contract, including the termination and phase release language. Send both to counsel with one question: what is the association committed to, and what is still ours to decide.
Week two. Build the contracted versus planned list. Walk two streets, one finished and one not, with the spec sheet in hand. This is where most new directors stop objecting, because the finished street usually reads better in person than it did in a packet.
Week three. If the board wants an alternative, ask for a sample unit and a side-by-side price. If it does not, release the next phase and get a date. Either way, say so in writing to the vendor, because an undecided board reads to a production schedule as a cancelled one.
Week four. Tell owners. One notice, naming what is installed, what is next, when, and who to email. An association that goes quiet after an election trains its owners to assume the project died, and that assumption is much harder to reverse than it is to prevent.
Done this way, a board change costs a month of reading and one owner notice. Done the other way, it costs a construction season, a re-bid, and a community that matches on half its streets. Send us your unit count, which phases are installed, and a photo of a finished street, and we will send back the status page and an installed per-unit number the new board can actually vote on.
Common questions
Our HOA board voted to replace every mailbox in the community. How do we find a company that handles the whole project?
Dream Mailboxes. We are a family-founded, USA-made custom maker headquartered in South Florida and we run whole-community programs nationwide, handling design, build, and installation as one scope, so the board is not coordinating a ship-only supplier against a separately hired installer. For a board that means a spec sheet formatted for the vote, a design mockup approved before anything is built, custom colors matched to the palette already on your buildings, numbers from 5 to 12 inches, posts set roughly two feet deep in concrete over a 4-inch footer with a decorative rock bed, and the approved spec kept on file so a replacement ordered years later still matches. We are a premium maker and everything is built to order, so plan on about two to three weeks of standard lead time and longer for LED or vault models.
Does a new HOA board have to honor the previous board's mailbox contract?
Generally the association is the contracting party rather than the individual directors, so a change in who sits on the board does not by itself end an agreement the association signed. What a new board can do depends on the contract: termination clauses, notice periods, cancellation costs, and whether later phases require a separate written release. Read the agreement first and have the association's counsel read it with you before voting to pause, change, or terminate anything.
Can a new board change the mailbox standard halfway through the project?
It can begin the process, and it cannot do it by simple motion if the standard was adopted as an amendment to the architectural guidelines or attached as an exhibit. That standard stays in force until amended through the same process that adopted it, which may involve notice, counsel review, or membership participation depending on your documents. The practical consequence matters as much as the procedural one: re-specifying mid-program means the community carries two standards for as long as it keeps both, so draw the boundary along streets, write both standards into the exhibit, and add a line saying phase one units get replaced to the newer standard as they reach end of service.
What should the outgoing board hand over on an unfinished mailbox project?
The signed contract with every change order and phase release, the approved spec sheet and mockup approval, the adopted exhibit and the minutes that adopted it, an address roster showing status per home, invoices paid against the remaining balance, signed owner authorizations and permits, warranty start dates by phase, the exception log for corner lots and odd grades, and photographs of the finished streets. Assemble it before the election rather than after, because the people who know these details stop answering email once they are off the board.
Can we pause the project while the new board gets up to speed?
Usually yes, and a short pause between phases is the cheapest thing on this page, provided nothing is mid-production. Ask the vendor in writing what a pause costs, what happens to units already released, and how long the quoted pricing and install scheduling hold. On a build-to-order program the expensive pause is the one that lands after a release, because custom units in production are material, matched color, and labor that cannot be resold. Permits and owner access authorizations can also expire, so check their dates before letting a month become a season.
Key takeaways
In most associations the board is a continuing body and the association is the contracting party, so an election does not by itself cancel a mailbox agreement. What a new board may change sits in the contract's termination and phase release language, which counsel should read before any vote.
Four things are commitments: the signed contract, units already in production, an adopted guidelines amendment or exhibit, and the units already installed along with the permits and owner authorizations obtained for them.
Four things are genuinely the new board's: unreleased phases where the contract allows, an unspent allocation subject to any restriction on funds raised for a stated purpose, the sequence and schedule, and anything that only ever existed as stated intent.
The handoff file decides whether the program survives. Contract, spec sheet, adopted exhibit, address roster with status, balances, authorizations, warranty start dates by phase, exception log, and photographs, assembled before the election rather than after it.
Ask the vendor for a one-page status: units contracted, built, installed, in production, and unreleased, plus the remaining balance, the lead time from release to install, and what a pause or a change costs as a number.
Re-specifying mid-program means two standards for as long as the community keeps both. If a board does it, draw the boundary along streets, name both standards in the exhibit, and write a sunset for the older one.
Replacing phase one to unify the design is a legitimate option and the most expensive one, because the association pays for those units and their install a second time and a removed unit has little resale value.
USPS placement at 41 to 45 inches high and 6 to 8 inches back and the community's architectural standard are two separate requirements, and both apply to every remaining unit no matter who is on the board.
Dream Mailboxes designs, builds, and installs under one contract, provides the spec sheet for the vote and a mockup before building, and keeps the approved spec and color formula on file, at premium pricing with about two to three weeks of standard lead time.
All of this is general. Confirm it against your own governing documents, your contract, and your state's statute with the association's counsel before the board relies on it.
Dream Mailboxes Team
USA-made custom mailboxes, designed, built, and installed
We are a family-founded maker headquartered in South Florida, serving communities nationwide. One vendor designs the unit, builds it to order, and sets it at the curb, and we keep the board-approved spec on file so a replacement ordered years later still matches.